Dashboard
Tuesday, 15 Sep 2026 | HEL-5 · demo snapshot
Today’s Commercial Sprint
Top 5 actions selected for your attention
| # | Issue / Action | Category | Area | Owner | Target | Exposure | Risk |
|---|---|---|---|---|---|---|---|
| 1 | OFCI documentation incomplete Request outstanding test certificates | OFCI | MEP | AM | Today 15 Sept | €850k | 95 |
| 2 | Contractor notice requires response Prepare a substantiated response | Notice | Both | SO | Tomorrow 16 Sept | €400k | 90 |
| 3 | Design change · switchroom Assess the change against the baseline | Variation | CSA | SP | In 2 days 17 Sept | €620k | 78 |
| 4 | Earthing design clarification Obtain a coordinated design response | Design | MEP | SO | In 3 days 18 Sept | €150k | 72 |
| 5 | Programme delay risk Review mitigation and delay evidence | Programme | Both | AM | In 5 days 20 Sept | €1.2m | 68 |
Emerging Risks
Illustrative risk review queue
Recent Intelligence
Example findings · not live AI analysis
Commercial Exposure
Amounts by current review stage
€1.27m
Submitted
€400k
Assessed
€650k
Approved
€448k
Disputed
€2.46m
Potential
Exclusive stages, not additive valuations of the same item.
Contractual Deadlines
Internal review targets · contract not verified
Project Health
Action status overview · not a predictive score
17OPEN ACTIONS
High risk4
Medium risk9
Low risk4
Closed1
Project Timeline
Selected source events in the demo record
Demo mode — synthetic data. Do not enter confidential information.